Project update November 2025
Project is progressing and as of November all of the points have been completed. In total 181 track panels refurbished and 38 left to do.
If you would like to get involved please come along on a Wednesday and talk to Jim Reeves who is leading the team. All are welcome.


The project to refurbish our 7 1/4″ track is progressing well. The refurbishment is lifting each track panel and replacing old wooden sleepers and clips with new recycled plastic sleepers and new track clips. Track bed is prepared and track panel re laid and levelled. You will probably notice the improved ride as you travel around the track.


Before
After